Kitty Hawk South Offshore Wind Project
PERMITTING DASHBOARD PROJECT POSTING DATE: MAY 12, 2022PROJECT WEBSITE: http://www.KittyHawkOffshore.com
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/14/2028
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Renewable Energy Production
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of Commerce, National Oceanic and Atmospheric Administration
Department of the Army, US Army Corps of Engineers - Regulatory
Department of the Army, US Army Corps of Engineers - Civil Works
Department of the Interior, Fish and Wildlife Service
Environmental Protection Agency
Description:
Update: In June 2022, the project name changed from Kitty Hawk Wind Project to Kitty Hawk South Wind Project to reflect the segmenting of the project.
Kitty Hawk Wind, LLC proposes to construct, own, and operate the Kitty Hawk South Offshore Wind Project. The Project will be located in the designated Renewable Energy Lease Area OCS-A 0508 (Lease Area). The Commercial Lease of Submerged Lands for Renewable Energy Development on the Outer Continental Shelf of Lease Area OCS-A 0508 was awarded through the BOEM competitive renewable energy lease auction of the Wind Energy Area offshore of North Carolina. The Lease Area covers 49,536 hectares (ha) and is located 44 kilometers (km) offshore of Corolla, North Carolina.
Update:
The Executive Director granted a Bureau of Ocean Energy Management request to extend completion dates for all actions on November 28, 2023. The Executive Director determination is posted here.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|